Information about current construction projects at Piedmont Triad International Airport is available below:
If you would like further information about construction project at PTI contact Mickie Elmore, 336-665-5600.
News from Development:
Fed Ex Site
FedEx contractor is installing the sort equipment for the Fed Ex Sort
Facility.
Taxiway Phase II
Blythe Construction is moving along well with Phase II of the
taxiway. The box culvert to reroute the
creek is completed. The roadway to
connect Cargo Road
with Rental Car Road
is graded and paved. The new cargo
access road structure is in place. Once
it is waterproofed the contractor will begin to place fill over top of the
structure for the Taxiway.
Runway Phase II
This work is well underway and includes the remainder of the
clearing and grubbing along with grading of the new runway. This work will continue for the next twelve
to eighteen months. Phase III will be
bid for paving and lighting of the new runway in the spring.
Bryan
Boulevard
The new "mainline" of Bryan Boulevard is open. There is a temporary entrance to the Airport
until the new bridge and ramp work is complete.
The temporary entrance will remain open for about two years.
Honda
Jet
The contractors and engineers have started work on Phase I
which is the initial grading and installing erosion control measures of the
Honda Site.