Information about current construction projects at Piedmont Triad International Airport is available below: If you would like further information about construction project at PTI contact Mickie Elmore, 336-665-5600.
Runway 5L/23R
Work continues on the new runway Project. The contractor is
installing lights and finishing pavement work. Earthwork for the runway should
be complete by the end of May.
Taxiway "E"
Work continues with stone being placed and the connection to
the existing Taxiway "J". Electrical conduit for taxiway lights is
being installed. New concrete for Taxiway "J" has been completed.
Taxiway "K" Extension
The connector into the FedEx ramp is complete. Stone is
being placed on the remaining portion in preparation for pavement.
Taxiway "D"
Work has started on Taxiway "D". Contractor is
clearing trees and installing Erosion Control Devices.